Assembly 2017-07-05T08:30:54+00:00

Mounting is carried out in several phases.

Ground Mounting:

  1. First, some meshes of the lower member are mounted by fixing rods to nodes and tightening the screws in the provided sphere holes;
  2. Then, the first diagonals are mounted using the same method described above, thus creating a first tetrahedron;
  3. Finally, a second tetrahedron is mounted and upper member spheres are connected by the rods;
  4. This sequence is repeated until all spheres and rods of the structure are mounted.

Overhead Lifting:

After the ground mounting phase, the overhead mounting needs to be performed.

The structure must be secured with textile ropes of appropriate capacity.

Lifting shall occur in two steps:

  1. First, the structure is lifted from the ground by few centimeters (inches) and kept hanging for a few minutes so to observe its performance and check its perfect flatness.
  2. If there are no issues with the first lifting, the final lifting and positioning of the structure can be carried out.
space frame structure

Steel space frame lifting

If the structure size prevents mounting in a single element, it shall be performed by segments.

Mounting methods of individual segments are similar to the ones described above.